All calculators

LoadCairn / Power & UPS

Battery Capacity & Runtime Calculator (Ah ↔ kWh)

Convert battery voltage and amp-hour capacity into gross and usable energy, then estimate runtime at a load in kW.

Inputs

Adjust the estimate

Results update as you change a value. Calculations run in this browser.

V
Ah
kW
%
%

Illustrative sample inputs: 48 V, 200 Ah, 2 kW, 80% depth of discharge, and 95% inverter efficiency. Edit them to match the battery data and expected load.

Calculated in this browser · No recalculation request · Works offline after load

Live results

Current estimate

Gross battery energy

9.6 kWh

Usable energy after DoD and efficiency

7.296 kWh

Gross energy × depth of discharge × inverter efficiency.

Runtime

3.65 h

Runtime in hours + minutes

3 h 39 min

Formula and calculation trace

Gross kWh = V × Ah ÷ 1,000 · Usable kWh = gross kWh × (DoD ÷ 100) × (inverter efficiency ÷ 100) · Runtime (h) = usable kWh ÷ load kW

  1. Gross energy = 48 V × 200 Ah ÷ 1,000 = 9.6 kWh.
  2. Usable energy = 9.6 kWh × (80% ÷ 100) × (95% ÷ 100) = 7.296 kWh.
  3. Runtime = 7.296 kWh ÷ 2 kW = 3.648 h, displayed as 3.65 h.
  4. Minutes = 3.648 h × 60 = 219 min after rounding to the nearest minute: 3 h 39 min.

Published source: Energy conversion, depth of discharge, rated capacity, battery condition, and inverter losses are covered by these manufacturer references: Victron Energy Dynamic ESS — Ah-to-kWh and depth-of-discharge calculation; Trojan Battery Lead Acid FAQs — capacity by discharge rate and temperature; Trojan Battery — Understanding AGM Ah Rating and capacity over service life; Victron Energy Phoenix inverter manual — battery capacity and inverter losses;

Assumptions and limits

  • The entered Ah value is the battery nameplate capacity at its rated discharge rate.
  • Lead-acid capacity falls at high discharge rates (Peukert effect), and all batteries lose capacity with age and temperature.
  • This is a planning estimate, not a runtime guarantee. It does not model a battery-specific discharge curve, cutoff voltage, or load changes.

Results are estimates for planning only, not a substitute for a licensed engineer's design or manufacturer data.