Standby generator sizing calculator.

For critical-facility engineers and facility managers, estimate standby generator real-power and apparent-power requirements from the running load, power factor, planning margin, and an optional motor-start allowance.

Load assumptions

Illustrative example · editable

The starting case is 100 kW, 0.80 load PF, 20% margin, and no motor-start allowance. These are editable examples, not site operating data.

Enter the connected or expected running real-power load above zero.

Use a measured or equipment-specified value when available.

An editable planning allowance applied to both calculated requirements.

Adds transient starting kVA on top of the full entered running load. It does not subtract that motor’s running demand.

Planning estimate only

Estimated capacity

Indicative load requirements and an illustrative 0.8-PF generator reference size.

Planning estimates updated. Required 120 kW and 150 kVA. Reference size 150 kVA.

Required real power · planning only

120 kW

Required apparent power · planning only

150 kVA

Next reference size · planning only

150 kVA120 kW at 0.8 PF

The reference ladder rounds up to 150 kVA. Actual manufacturer ratings and availability vary.

Checking Pro access…Download generator sizing reportExport CSV

Estimates for planning only, not a substitute for a licensed engineer’s design or manufacturer data.

Next: how long will your fuel last? Generator fuel burn & runtime →

Formula

Required kW = total load kW × (1 + margin % ÷ 100). Required kVA = (total load kW ÷ load PF + motor-start allowance kVA) × (1 + margin % ÷ 100). Reference size = the first ladder rating ≥ max(required kVA, required kW ÷ 0.80).

Live calculation trace · planning only

  1. Running load: 100 kW ÷ 0.8 PF = 125 kVA.
  2. Required real power: 100 kW × 1.2 = 120 kW.
  3. Required apparent power: (100 kW ÷ 0.8 PF + 0 kVA motor-start allowance) × 1.2 = 150 kVA.
  4. Size basis: max(150 kVA, 120 kW ÷ 0.80) = 150 kVA.

Assumptions and limitations

Planning estimate only

The optional motor-start value is an additive transient kVA allowance on top of the full entered running load. This simplified model does not subtract the motor’s running demand if it is already included in total load.

Motor-start performance depends on the motor, starter, concurrent load, and acceptable voltage and frequency dip. The 0.8-PF generator rating and size ladder are illustrative; actual manufacturer offerings and ratings vary.

This estimate does not model altitude or temperature derating, step loading, or harmonics. It is not equipment selection, engineering design, code compliance, or a guarantee. Have a qualified generator supplier or electrical engineer evaluate the actual load profile and site.

Source notes

Planning references · not endorsements

NFPA 110, Standard for Emergency and Standby Power Systems

The relevant system standard for emergency and standby power systems. NFPA 110 does not endorse this calculator or its simplified formula.

Cummins, “How to size a genset”

Explains the relationship between kW and kVA and why motor starting, environmental conditions, and step loading affect generator selection.

Caterpillar commercial generator sizing guide

Outlines a more detailed manufacturer process based on the actual loads and installation site.

Method / Facility demand

Build the scenario from the whole facility

Standby sizing needs to account for both real and apparent power across facility loads, including UPS systems, cooling, pumps, fans, lighting, controls, and other auxiliaries. Treat this calculator as an early scenario screen while a complete load schedule or generator study is being developed.

Keep the source of each demand value clear: label it as nameplate, measured, or modeled-peak demand. Do not combine those bases without recording which one each value represents.

Required kW is the scenario’s real-power demand after the entered margin. Required kVA is its apparent-power demand after the power-factor conversion, optional motor-start allowance, and margin. Read them as separate planning requirements to compare against published generator ratings, not as a selected generator model.

Review / System boundaries

Account for site and transient conditions

Confirm the manufacturer’s published rating conditions for the installation and assess site derating against that rating basis. Check step loading and transient recovery, not only the steady-state kW and kVA totals.

A detailed review also needs to consider nonlinear or unbalanced loads, neutral current, short-circuit coordination, and protection settings. Plan fuel autonomy, emissions, acoustics, enclosure, transfer equipment, paralleling, redundancy, availability, and installation constraints for the site.

Have a qualified engineer or generator supplier review the actual load profile and starting sequence, site conditions, transfer equipment, applicable standards, and manufacturer data before selecting equipment.

Planning guide / generator-sizing

Introduction

The standby generator sizing calculator estimates required real power and apparent power from total running load, power factor, a growth or safety margin, and an optional motor-start kVA allowance. It also rounds the larger of two planning requirements to the next value in the page’s reference-size ladder at 0.8 power factor. Use it to make a load scenario explicit before discussing a generator with a supplier.

The starting values are 100 kW total load, 0.80 power factor, 20% margin, and no motor-start allowance. The calculator keeps the real-power requirement and apparent-power requirement separate. If the optional motor-start entry is used, it is added to the running apparent load before the margin is applied.

The reference rating and size ladder are illustrative. The calculator does not evaluate the actual load sequence, site derating, short-circuit behavior, transient recovery, emissions, fuel autonomy, transfer equipment, redundancy, acoustics, or manufacturer-specific operating ratings. Use the result to frame an engineering and supplier review, not as equipment selection.

Method / Calculation

How it works

First, running apparent power is total real-power load divided by the entered power factor. A lower power factor therefore produces a larger kVA value for the same kW input. This conversion is a simplified steady-state representation and assumes the selected power factor describes the full entered running load.

Required kW multiplies total load by one plus the margin percentage divided by 100. Required kVA adds the optional motor-start allowance to running kVA and then applies the same margin factor. The page’s assumption is additive: it does not subtract the motor’s running demand from the total even if that motor may already be included there.

The calculator converts required kW into an equivalent 0.8-PF reference kVA by dividing by 0.80. It compares that number with required kVA and uses the larger value as the reference requirement. It then selects the first published value in its internal illustrative ladder that is greater than or equal to the reference requirement.

The ladder returns an example rating and a corresponding reference kW at 0.8 PF. It is not a catalog of current products or a promise that a specific rating is available. Manufacturer ratings, conditions, and selection practices must be confirmed for the site and load profile.

Running kVA = total running load kW ÷ load power factor

Margin factor = 1 + margin % ÷ 100; required kW = total kW × margin factor

Required kVA = (running kVA + optional motor-start kVA) × margin factor

Reference kVA = max(required kVA, required kW ÷ 0.80)

Reference size = first value in the calculator ladder ≥ reference kVA

  1. Sum the running real-power load for the scenario and enter that total in kW. Label whether it is measured, nameplate-based, or modeled peak demand.
  2. Enter a power factor that represents the same load condition. The calculator requires a value above zero and no more than one.
  3. Set the margin from the planning scenario. The page accepts zero through 100 percent; the margin is applied to both required kW and required kVA.
  4. Add a motor-start allowance only when the scenario calls for it. Treat it as an additive transient kVA allowance and note that the calculator does not remove the motor’s running load from total load.
  5. Read required kW, running kVA, and required kVA separately. Convert required kW to the 0.8-PF reference kVA and compare the two criteria.
  6. Use the rounded reference size as a discussion point only. Review the complete load schedule, starts, site conditions, generator rating basis, and manufacturer data before selecting equipment.

The page cites NFPA 110 context and manufacturer references as planning sources, while stating that the simplified formulas are not endorsed by those sources. Use the actual owner requirement, load profile, and published generator ratings in the engineering review.

The calculator’s additive motor allowance, 0.8 reference power factor, and internal size ladder are explicit assumptions. Preserve them in the scenario record so a reviewer can distinguish calculator arithmetic from the final design basis.

Compare required real power and apparent power as separate constraints. The reference size shown by the page is selected from its own size ladder after the calculator has applied the entered margin; that does not confirm a specific manufacturer model, voltage, enclosure, fuel system, altitude rating, or transient response. If the load has large motors, UPS rectifiers, transformers, or staged additions, capture those conditions in the load schedule and review how they affect both steady operation and starting events. The optional motor allowance is added to the apparent-power scenario; it is not a dynamic simulation and does not remove the motor from the running-load input.

Calculation trace / Illustrative inputs

Fully worked example

Illustrative calculation using the page’s initial values: 100 kW running load, 0.80 power factor, 20% margin, and no motor-start allowance. This follows the calculator’s displayed default result.

  1. Running kVA = 100 kW ÷ 0.80 = 125 kVA.
  2. Margin factor = 1 + 20 ÷ 100 = 1.20. Required kW = 100 kW × 1.20 = 120 kW.
  3. Required kVA = (125 kVA + 0 kVA) × 1.20 = 150 kVA.
  4. Required kW at the 0.8-PF reference = 120 kW ÷ 0.80 = 150 kVA. Reference requirement = max(150 kVA, 150 kVA) = 150 kVA.
  5. The first ladder value greater than or equal to 150 kVA is 150 kVA, corresponding to 120 kW at the calculator’s 0.8-PF reference.

Illustrative calculator result: 120 kW required, 150 kVA required, a 150 kVA reference requirement, and an illustrative 150 kVA / 120 kW ladder size.

The example excludes site derating, load sequence, motor transients, harmonics, transfer equipment, and actual catalog ratings. Planning estimate only; confirm the full duty and manufacturer conditions with a qualified engineer or supplier.

Review / Input checks

Common mistakes

Questions / Planning use

Frequently asked questions

Why does the calculator show both kW and kVA?

They express different sides of the planning scenario. The tool calculates real-power demand in kW and apparent-power demand in kVA using the entered power factor and optional motor-start allowance.

How is the optional motor-start allowance applied?

It is added to running kVA and then the margin factor is applied to the sum. The page does not subtract the motor’s running demand from total load if it is already included.

What does the 0.8-PF reference size mean?

The calculator divides required kW by 0.80 and compares that reference kVA with required kVA. It then rounds up using an internal illustrative size ladder; this does not select a manufacturer product.

Does the margin cover altitude or temperature?

No. The margin is a multiplier applied to the entered load calculations. Site derating and generator rating conditions require a separate review against manufacturer data.

Which source basis should be used for final sizing?

The calculator’s notes cite NFPA 110 context and manufacturer references, while saying the simplified formula is not an endorsement. Use the project load schedule, owner requirements, and actual generator data with qualified review.

Continue / Related tools

Join the calculator waitlist